Lower Lake’s Restoration, Part 4, 2013

January, February, 2013Emails flew back and forth between myself and Kodiak, the Lot 9 owner, Matrix Engineering, John Matricardi, Dan Willhoite of Medina County Engineers, and of course, my attorney, David Riehl as the dam restoration plans were refined for approval.¬† Finally February, 28th the plans were declared acceptable and were mailed to me in… More Lower Lake’s Restoration, Part 4, 2013

Lower Lake’s Restoration, Part 3

October, 2012On October 26, I used photos to measure approximate tree heights for the trees on the dam that Kodiak would need to remove.¬† Bramhall had already marked each tree that needed to be removed from the dam with the fluorescent bright pink spray spot, and had provided trunk diameter¬†measurements, so the heights of the… More Lower Lake’s Restoration, Part 3